In the 7.3 (Quality and Risk Management plan 1st version) deliverable the project partners defined the process of quality and risk identification, assessment and evaluation implemented during ZEvRA project for ensure the consistent quality of all project outputs, in order to fully meet the commitments (objectives and deliverables) made in the Grant Agreement. The document includes the Risk Register initial version, with the identified risks, their possible affects, owners, ranking and measures to diminish the negative impacts. The risk owners actualize the table every two month and the Technical Board monitoring those during its meeting. Because during the first period of the project, the used process proved suitable and usable, there is no need to modify. The up-to date Risk Register indicate the recent risks and respond plans to mitigate the identified risks.